Size a transformer from the expected electrical demand in kVA, then verify starting duty and site conditions. A list of equipment kW ratings is not a complete transformer specification. The first calculation estimates the load; it does not by itself approve a transformer, protective device or cable.

This guide is for buyers preparing a technical enquiry and engineers reviewing the inputs. The worked values are illustrative, not a recommendation for a particular installation. Final selection must follow the project study, utility requirements, applicable rules and the manufacturer’s guaranteed duty.

Start with the right power value

Real power, measured in kW, describes useful electrical power consumed by the load. Apparent power, measured in kVA, combines voltage and current. Power factor relates them: kVA = electrical input kW ÷ power factor. Use the actual operating power factor, not an assumed figure copied from another project. Schneider Electric provides this relationship in its transformer calculation guidance.

A motor’s shaft rating is mechanical output, not electrical input. If only shaft kW is available, first divide it by the motor efficiency at the relevant duty, then account for power factor. For example, a 75 kW shaft load at 94% efficiency and 0.86 power factor represents approximately 75 ÷ 0.94 ÷ 0.86 = 92.8 kVA at that operating point. Motor and drive supplier data are preferable to an assumed efficiency.

If nameplate kVA or measured RMS voltage and current already establish apparent power, do not divide by power factor again. With distorted waveforms, distinguish true power factor from displacement power factor; a simple sinusoidal power triangle does not describe every harmonic effect.

Sinusoidal load example showing 360 kW, 400 kVA and power factor 0.90, with approximately 174 kvar reactive power
Original calculation illustration. The power triangle assumes sinusoidal voltage and current; it is not a harmonic loading model or a transformer nameplate.

Calculate from voltage and current when they are known

  • Single phase: kVA = V × A ÷ 1,000.
  • Balanced three phase: kVA = √3 × line-to-line V × line A ÷ 1,000.
  • Three-phase current: A = kVA × 1,000 ÷ (√3 × line-to-line V).

For example, a balanced 500 kVA load at 400 V corresponds to approximately 722 A. This is a load-current calculation, not a cable or breaker selection. Uneven phase loading, neutral current and harmonics require separate checks. The same arithmetic applies at 50 Hz and 60 Hz, but a transformer must still be designed and rated for its actual supply frequency. See our 50 Hz and 60 Hz selection guide.

Turn the connected load list into a design demand

For each circuit, record electrical input power or current, operating power factor, duty cycle and which loads run together. Keep normal running, emergency operation and starting sequences distinct. The designer should justify any utilization or coincidence factors using the operating plan and local requirements. There is no single reduction factor suitable for every factory, building or pumping station.

For mixed linear loads, combine real and reactive power consistently before deriving the total apparent power. Adding individual kVA values is a conservative screening method for many ordinary loads, not always the exact coincident demand. Do not use monthly energy consumption in kWh as if it were the maximum kW or kVA demand.

A worked screening example

Assume a study has established a coincident electrical input of 360 kW at 0.90 power factor: 400 kVA. A confirmed expansion adds 60 kW, also at 0.90 power factor and operating simultaneously. Under these stated assumptions, the combined demand is (360 + 60) ÷ 0.90 = approximately 466.7 kVA.

A 500 kVA unit could therefore be a candidate for further review if that rating is available and acceptable for the project. It is not yet an approved selection: starting voltage dip, harmonic duty, thermal conditions, utility constraints and the required service margin may change the result. The extra 60 kW is a planned load in this example, not a universal allowance.

Capacity screening sequence from 400 kVA present demand to 466.7 kVA with a stated expansion, then checks before considering a 500 kVA transformer
Illustrative screening sequence. Every load and power-factor assumption is stated; the final rating remains subject to engineering checks.

Check motor starting before confirming the rating

Give the engineer the largest motor’s rated voltage, running current, starting method, supplier starting-current data, acceleration time and starts per hour. Also identify the load already connected when that motor starts. Eaton’s selection guidance treats motor service separately from a basic running-load kVA calculation; product-specific sizing tables must not be applied indiscriminately to another transformer family.

A starting assessment considers source strength, transformer impedance, cable impedance, starting power factor and acceptable voltage at the motor and other loads. A soft starter or variable-frequency drive changes the starting duty, but its actual settings and input characteristics still matter. Motor-starting current is not the same phenomenon as transformer magnetizing inrush when the transformer itself is energized.

Do not use oversizing as a substitute for a study

Too little capacity can leave inadequate thermal or voltage-dip margin. A larger unit can increase purchase cost, installed space and no-load loss; downstream fault duty must also be reviewed. Compare guaranteed losses and the expected operating profile rather than assuming the largest rating is the most efficient choice.

Specify ambient temperatures, altitude, ventilation or enclosure restrictions, harmonic-producing loads and cooling duty. Review our temperature-rise guide and impedance selection article where those conditions are material.

What to send for a capacity review

Start with the destination country, primary and secondary voltages, frequency, load type and available kW, kVA or current figures. If relevant, add a motor or drive schedule and a description of future expansion. A complete drawing package is not required to start; identify unknown values rather than guessing them.

For outdoor oil-filled duties, review the 11 kV oil-immersed transformer range. For a proposed indoor installation, compare the project requirements against our cast-resin dry-type transformer information; capacity alone does not determine the appropriate construction.

Ask Apex to review your transformer capacity requirement. Send the information you have; drawings and attachments are optional.

Technical references