A replacement transformer needs an electrical match and a physical fit. Compare the approved ratings, terminal arrangement, cable approach and installation envelope before ordering. The old nameplate is a useful starting point, but it does not define every dimension needed to connect and install the replacement.

This checklist is for procurement and design coordination, not an installation procedure. Site inspection, opening compartments and measurements near electrical equipment must be arranged by qualified personnel under the owner’s isolation and safety procedures. Do not open an energized compartment to take a photograph.

Confirm the electrical duty first

Start with the existing nameplate and the new operating requirement. Check rated power, all winding voltages, frequency, vector group, neutral arrangement, tap schedule, impedance and cooling ratings. Identify whether the new unit replaces an isolated transformer or will operate in parallel. An increase in MVA also requires review of the connected system and interfaces; it is not simply a larger nameplate.

Use our nameplate guide to read the ratings. Where parallel operation is required, review the ratio, phase displacement and impedance checks with the project engineer.

Describe the cable connection before the terminal box is designed

State whether cables enter from below, above or the side. Record the cable type, conductor material, cross-section, outside diameter and number of runs for each phase and neutral. Include the lug dimensions and hole pattern if existing terminations must be retained. Label photographs with their viewing direction so that left and right cannot be confused.

Check the available cable approach against the cable manufacturer’s bending-radius requirements and the proposed lug position. Conductor cross-section alone does not establish the required bending space. Cable supports and the connection design must also prevent cable weight or movement from imposing unacceptable loads on transformer terminals or bushings. Eaton’s liquid-immersed substation transformer manual specifically warns against treating an LV bushing as a structural support.

Conceptual front view identifying cable entry area, entry-to-terminal height, termination geometry and support checks
Conceptual interface checklist, not a wiring diagram or the Nigeria unit’s terminal layout. No dimensions or cable ratings are specified. Open the image to enlarge it.

What the Nigeria replacement order illustrates

Our Nigeria 5 MVA replacement case specified an oil-immersed step-up transformer with one 11 kV winding and two 0.4 kV windings. The customer’s incoming cable requirement was 32 single-core 500 mm² cables: eight each for A, B, C and neutral N.

That schedule explains why the connection interface matters. It does not state the MVA allocation between the two low-voltage windings or how those cables are divided between them. Neither should be inferred from the overall 5 MVA rating or the photographs; the winding schedule and connection drawing must resolve them. The cable count is a project requirement, not a standard arrangement for every 5 MVA transformer.

Workshop photograph of the open terminal compartment supplied for the Nigeria 5 MVA transformer replacement case
The supplied workshop photograph shows the accessible terminal compartment. It does not establish cable ampacity, winding allocation or site commissioning status.

Compare the installed envelope with the existing site

Obtain an outline drawing showing the tank, radiators, terminal boxes, accessories, base or rail interfaces and cable entries. Compare these with the available site space. Confirm the operating mass and support requirements with the civil designer; matching the old tank dimensions does not prove that an existing foundation is adequate.

Allow for cooling, door opening, maintenance and the removal route as separate requirements. Review the delivery dimensions and mass against access openings and the handling plan. Do not adopt a universal wall clearance or bending-space value from this article: the equipment drawings, manufacturer’s instructions, applicable rules and site design govern the actual installation.

Conceptual transformer plan comparing the main tank, radiators, terminal box and service envelope
Plan-view concept, not an anchor template. Verify fixing or rail locations and all dimensions against the approved drawing.

Send the information you have

For an initial enquiry, send the old nameplate, destination country and a short description of what must change. Add safely obtained terminal photographs, a cable schedule and any outline or foundation drawing you already hold. Unknown dimensions can be identified during technical review; a complete drawing package is not required to start.

For an 11 kV oil-immersed transformer, distinguish the required supply duty from the old unit’s rating. For a 20/24 kV oil-immersed transformer, state the actual winding voltage and project insulation requirements rather than treating the voltage-class label as a complete specification.

Discuss a replacement transformer. You can start with the nameplate and project location; drawings and attachments are optional.

Technical references

These manufacturer documents support the interface checks above. They cover different equipment types; their product-specific dimensions and instructions are not interchangeable.